Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What interfaces will be required to use capacity acquired?

acquired interfaces
0
10 Posted

What interfaces will be required to use capacity acquired?

0
10

Once capacity is secured Users will be required to submit Mid Channel Nominations (MCN) to both National Grid & RTE separately. The MCN submitted to National Grid should be a copy of that submitted to RTE and vice versa.