Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What if the contractor mobilizes to install wells that were requested by OPS in the CAP request, but also wants to conduct a pilot test at the same time. How should the costs be coded?

0
Posted

What if the contractor mobilizes to install wells that were requested by OPS in the CAP request, but also wants to conduct a pilot test at the same time. How should the costs be coded?

0

Costs relating to the assessment activities (i.e. well installation) must be separated from costs relating to the pilot test. The assessment costs will be included in a reimbursement package to be processed the old way. The pilot test costs will be included in a reimbursement package with an attached E-RAP.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123