Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What if the Contract includes one schedule of rate, but it is not appropriate eg. clearing of trees ?

0
Posted

What if the Contract includes one schedule of rate, but it is not appropriate eg. clearing of trees ?

0

A new rate is not to be added because the scope of the activity (ie tunnel excavation) is not within the Schedule of Rates (and is therefore part of the lump sum price, unless a Variation applies). That is, the requirements of clause 30.4.1 have not been satisfied.