What happens to the Federal Facility Agreement (FFA) schedule and commitments when the Army awards a PBC contract?
The PWS requires contractors to adhere to the requirements spelled out in the FFA schedules and commitments as they apply to the sites included in that contract. If changes in the schedule are required as a result of a change in approach, the contractor is required to work with the Army and FFA parties to resolve the work schedule issue. The goal will be to meet the FFA schedule; however, if a modification is necessary, the contractor and the installation Environmental Coordinator will coordinate with the FFA parties to develop an alternative schedule and modify the schedule, if warranted.