What happens if Systemwalker CentricMGR shifts a startup day to a holiday?
In that case, it shifts the startup day by one more day. For example, suppose your system shifts start dates to the previous day when they fall on a holiday. If the startup day is on Monday and Monday is a holiday, the new startup day will be Sunday. However, if Sunday has been set up as a holiday, the startup day will be shifted to Saturday, and if Saturday has been set up as a holiday, the startup day will be shifted to Friday. You can specify the maximum number of days that the system can shift.