Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What happens if I need to get approval for an urgent Project Change Request, and the approval authority won’t be meeting for 2 weeks? Is there a way to fast track the request?

0
Posted

What happens if I need to get approval for an urgent Project Change Request, and the approval authority won’t be meeting for 2 weeks? Is there a way to fast track the request?

0

In case of an urgent change, it is possible to use an alternate method of obtaining approval; e.g., contacting approval authorities via e-mail. However, the CCS Project Change Control Procedure still needs to be followed, and a Project Change Request needs to be completed and logged.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123