What did the Net Present Value (NPV) costs analysis include and not include?
This financial analysis took a conceptual look at the 20 year life cycle for a 50 mgd SWRO plant and included overall treatment costs such as intake and distribution power, chemicals, maintenance, replacement, labor, capital costs and interest on capital. The analysis did not include land, depreciation, distribution improvements or intake capital costs and it assumes co-location with an existing power plant or other existing intake system.