What controls will be used to ensure only suitable contaminated soil will be transported to the CSR?
Extensive sampling will be undertaken onsite prior to transportation to Innova’s centre in accordance with EPA requirements. An environmental report will be required detailing type, extent and quantity of contaminated soil intended to be transported to the CSR. All loads of soil will be examined on arrival and additional samples taken for Innova’s internal quality control with any soil deemed unacceptable returned to the site of origin. Once treated, an independent consultant will test the soil with results compared to clean fill criteria. Only hydrocarbon contaminants will be accepted to the centre with unsuitable material including elevated heavy metals and asbestos not accepted to the centre. Additional information can be found below.