Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What are the steps involved in securing authority to build this transmission line?

0
Posted

What are the steps involved in securing authority to build this transmission line?

0

• Need determination – In the case of CREZ transmission facilities, the PUCT has already established the need for new and additional transmission capacity. • Route identification – Lone Star performed engineering, routing and environmental assessments to evaluate potential transmission line routes. Lone Star anticipates that PUCT will take into consideration input from the public, as well as federal, state and local governments prior to the PUCT selecting a route. • Certification – Lone Star must apply to the PUCT for approval, or certification, to construct its new transmission line. Lone Star has proposed several alternative routes for PUCT review and addressed issues of cost; transmission engineering; real estate and land use; finance/risk management; environmental; and legal/regulatory concern. The PUCT will decide whether to approve the application and which route Lone Star should use. • Construction – Once the plan has been approved and easements have been obtained, construction

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123