Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What are the standard tie and façade brace arrangements for independent tube and fitting scaffolds?

0
Posted

What are the standard tie and façade brace arrangements for independent tube and fitting scaffolds?

0

Basic scaffold ties for independent and putlog scaffolds should be fitted: • On the first standard and then on alternate standards horizontally • At alternate levels with a maximum vertical interval of 4m • At the top platform level for sheeted and debris netted scaffolds. If the above cannot be achieved then design advice should be sought! Façade bracing should be placed every five bays.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123