What are the requirements for decommissioning FERC-licensed hydrokinetic facilities?
You must comply with the decommissioning requirements in your MMS-issued lease. If you fail to comply with the decommissioning requirements of your lease then: (a) The MMS may call for the forfeiture of your bond or other financial assurance; (b) You remain liable for removal or disposal costs and responsible for accidents or damages that might result from such failure; and (c) The MMS may take enforcement action under §285.400 of this part. § 285.904 Can I request a departure from the decommissioning requirements? You may request a departure from the decommissioning requirements under §285.103. Decommissioning Applications § 285.905 When must I submit my decommissioning application? You must submit your decommissioning application upon the earliest of the following dates: (a) 2 years before the expiration of your lease. (b) 90 days after completion of your commercial activities on a commercial lease. (c) 90 days after completion of your approved activities under a limited lease on a R