What are the prime contractors responsibilities, regarding the DBE Program and the payments they make to their subcontractors?
All payments made to any subcontractor on an MDT Federally funded project must be reported to the MDT DBE Program Manager. The information included should be, project number and designation, Prime’s name, subs name, date of payment, amount of payment, and the line items being paid. These must be submitted monthly.
Related Questions
- WHAT IS THE RELATIONSHIP BETWEEN PAYMENTS BY THE CORPS TO THE PRIME CONTRACTOR AND PAYMENTS TO SUBCONTRACTORS BY THE PRIME CONTRACTOR?
- What are the prime contractors responsibilities, regarding the DBE Program and the payments they make to their subcontractors?
- do the requirements apply to prime contractors only or to subcontractors also?