What are the plan checking turn-around (time to complete review) standards?
The Placer County plan check turn-around goal is to complete the first plan check review process within 4-6 weeks from the date of application. Subsequent reviews, due to such things as corrections required, are to be completed within 2-3 weeks from re-submittal date. Turn-around time is defined as “the time elapsed from date of application, or re-submittal, to the date plan check comments are generated or permit issued.