What are the key milestones of the planning process?
After receipt of an outline planning application a the District Council must process the application and reach a decision within 16 weeks. After the outline has been granted further permissions must be sought in order to implement the detail of the scheme. These permissions are known as applications of ‘reserve matters’ and will be subject to a 13 week decision period (16 weeks if an additional EIA is required).