What are the deadlines to lien a job?
Mechanics liens must be filed within 120 days from the completion of the project. They can be filed prior to a project reaching completion and anytime before the 120 days deadline. However if a Notice of Completion is filed, then the timeframe for filing the lien is changed to 60 days. Be advised that anyone who sent a 20-day notice should receive a copy of the Notice of Completion. Please review Arizona Revised Statutes 33-993 Time Frames to Follow Construction Law, according to Arizona Revised Statutes 33-981(D), provides a time frame in which contractors and sub-contractors can retain their lien lights. If this time frame is not followed a contractor/sub-contractor will forfeit said lien rights. When a job is started, a contractor/sub-contractor has 20 days to give notice that he is working on a job. This notice must be sent with proof of mailing to the owner of the property, the general contractor (if a sub is mailing notice), and the lender involved (if any). The notice states tha