What are the curing requirements after stripping?
Test cubes will be taken on site with the mortar mix design specified for your project. When the formwork is removed, the walls have a strength of between 1.5 to 2.0 mPa. Within 28 days, the walls will have cured to an ultimate strength of between 10 to 20mPa, depending on the mix design of the mortar, or the cement: water ratio.