What are the allowable construction loads that can be placed on top of the existing piers?
Per Special Provisions 10-1.26N, the Contractor shall provide full design evaluations of the shaft and foundations in terms of load carrying capacity of the elements to which the temporary supports are being anchored, and the lateral stability to the overall column. 11) What are the allowable construction loads that can be placed on the existing spandrels? See previews response. 12) Page 78. Special Provisions, Order of Work. a) When can the erection of precast concrete pile cap shells of the eastbound concrete trestle from bents e.g. through 37 commence? See future new combined contract for Richmond-San Rafael Bridge. b) Has the precast concrete pile cap shell been designed to be completely filled with concrete in one pour? The precast concrete pile cap shell has been designed to be completely filled with concrete in one pour. The flexure and shear design of the precast concrete pile cap shell was performed using a simply supported span between centerlines of the CIDH piles. Attention