What are examples of actions that, if they occur on or after June 25th, WILL NOT TRIGGER the section 508 procurement obligations?
• Delivery of EIT purchased under a contract awarded or order placed prior to June 25, 2001. • Within-scope modifications for the acquisition of EIT under contracts awarded before June 25, 2001 (e.g., small increases in the number of units ordered or changes to the delivery schedule). • Exercise of unilateral options to acquire EIT under contracts awarded before June 25, 2001. • Determination of funds availability on a multiyear contract awarded prior to June 25, 2001. • Award of an IDIQ contract, except for requirements that are to be satisfied by the initial award.