Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Weve estimated the retaining wall quantity to be more than the quantity specified. Will the quantity be revised through addendum?

0
Posted

Weve estimated the retaining wall quantity to be more than the quantity specified. Will the quantity be revised through addendum?

0

No, the estimated quantity will not be revised by addendum. The estimated quantity for the Retaining Wall Modular Concrete should have been 23,405 SF (Phase 1A: 16,110 SF, Phase 1B: 7,295 SF). Final payment will be for the measured and accepted quantity.