Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

The RFP requires the offeror to propose costs for Facility Modifications (other than the GFP facilities). Are these costs to be included as part of CLINS 1-5 “Basic Contract Award”?

0
Posted

The RFP requires the offeror to propose costs for Facility Modifications (other than the GFP facilities). Are these costs to be included as part of CLINS 1-5 “Basic Contract Award”?

0

Yes, the costs associated with facility modifications (including modifications to Government-furnished facilities if required) should be included in the total price of CLINs 0001 through 0005A. However, these costs (facility renovation, alteration, build-out, etc.) should be identified separately in the price proposal.

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123