The building department requires a District job number (J#) prior to structural demolition. What is a job number?
Because asbestos has been used in many structural applications, District Regulation 11-2-401.3 requires that for every demolition or for every renovation involving the removal of 100 sq ft/lin ft or greater of Regulated Asbestos Containing Material (RACM), a notification must be made to the BAAQMD at least 10 working days prior to commencement of demolition/renovation. For residential buildings of four or fewer dwelling units, 72 hour prior notification is acceptable with the payment of an additional fee (see schedule below).