Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

The audit is complete but there are unspent bond proceeds. Can the remaining funds be spent on the project?

0
Posted

The audit is complete but there are unspent bond proceeds. Can the remaining funds be spent on the project?

0

No further purchases from the construction account are allowed once the final audit is conducted. Refer to Section 11 (7) of the Rules for Major Capital School Construction Projects regarding disposition of unexpended bond proceeds.