Since the RFO has been delayed, will new projects and or companies be allowed to enter the RFO if they had not met the previous set of criteria submittals, interconnects & NOI?
Yes, new projects and/or companies will be allowed to participate in the RFO process provided they submit for gas and electric interconnections. The extension of the deadline to file for gas and electric interconnection studies is March 28. The Notice of Intent (NOI) was voluntary and not a requirement of the RFO process.