Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Since the RFO has been delayed, will new projects and or companies be allowed to enter the RFO if they had not met the previous set of criteria submittals, interconnects & NOI?

0
Posted

Since the RFO has been delayed, will new projects and or companies be allowed to enter the RFO if they had not met the previous set of criteria submittals, interconnects & NOI?

0

Yes, new projects and/or companies will be allowed to participate in the RFO process provided they submit for gas and electric interconnections. The extension of the deadline to file for gas and electric interconnection studies is March 28. The Notice of Intent (NOI) was voluntary and not a requirement of the RFO process.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123