Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Should I discuss with the OPS reviewer projected labor hours for Remediation System Design (PWC 3B) and CAP Report Preparation (PWC 3C) prior to preparing the CAP?

0
Posted

Should I discuss with the OPS reviewer projected labor hours for Remediation System Design (PWC 3B) and CAP Report Preparation (PWC 3C) prior to preparing the CAP?

0

Yes; following completion of approved pilot testing the consultant and/or owner/operator should contact the OPS reviewer, prior to preparing the CAP to discuss anticipated PWC 3B and 3C costs. These costs will reflect the anticipated level-of-effort associated with the remediation method agreed upon by the consultant and OPS.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123