Please reference Contract Drawings T-4 & T-5. Will the future crosses installed by the FRS II contractor at Elev 756 within each of the two shafts be bulkheaded on the sides and top as installed?
The FRS II contract stipulates making air available to the MTPT Contractor for ventilation purposes. The FRS II contractor is required to coordinate and cooperate with the MTPT Contractor. The MTPT Contractor is required to coordinate with the FRS II contractor per Contract Documents, Section 01001, Part 5.5 and Section 01010, Part 1.04. 2008-06-19 Since the pressure testing bulkheads will have been removed prior to tying into the existing pipes, will the welded and inspected pipes between the former steel bulkheads and the ties into the existing lines require any subsequent pressure testing? No, provided the closure pieces are less than 20 feet long.
Related Questions
- Please reference Contract Drawings T-4 & T-5. Will the future crosses installed by the FRS II contractor at Elev 756 within each of the two shafts be bulkheaded on the sides and top as installed?
- I installed Reference Manager and see the menu options in the Tools menu of Microsoft Word, but I don’t see the toolbar. Where is it?
- Why is it important to use fixed common reference point for dimensioning of drawings?