Loadcases T1 and T2 already existed under a linear analysis and AutoPIPE could not create duplicate loadcases with the same name. So, it renamed the cases as $T1 and $T2. Please note that when you ran a non-linear analysis and established user cases T1 and T2 the other T1 and T2 cases did not exist. But when you ran a linear analysis, and T1 and T2 were created. AutoPIPE renamed your existing user T1 and T2 cases to avoid a programming conflict.