Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Is there a no-instream work date at every bridge or culvert project within a stream?

bridge culvert project stream
0
Posted

Is there a no-instream work date at every bridge or culvert project within a stream?

0

No, all bridge and culvert permits do not require a no-instream work date. No-instream work dates are generally used where impacts to fisheries habitat and resources could occur at certain times of the year, as a result of the permitted activity. Work can still be performed behind cofferdams; however, the cofferdam must be installed before the no-work period. 15.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123