Is one month for contract negotiation a requirement or a goal?
It is a PUC requirement, but it is subject to some modification and we may see some extension of that one month. 23) Question: Please elaborate on Table 3.1 of the “solicitation goals” and 1-2% of PG&E’s load. Answer: 1% of our load is approximately 700 Gigawatt hours. At a 100% capacity factor, that translates to 80 Megawatts.For a 20% capacity factor project that translates to 400 Megawatts to supply 1% of our load.So depending on capacity factor, 1-2% of load could equate to 80 to 800 Megawatts of capacity.There is detailed information listed on that in the green books so you can see the breakdowns that show what 20, 40, 60, 80, and 100% capacity factors translate to in terms of Megawatts.