Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Is additional environmental review required when the final action is different from the alternatives analyzed in an EIS?

0
Posted

Is additional environmental review required when the final action is different from the alternatives analyzed in an EIS?

0

If the final approved proposal falls within the range of alternatives analyzed in the EIS and all likely significant adverse impacts have been evaluated, additional review would not be required. For example, one of the EIS alternatives evaluates the impacts of four urban centers and another alternative evaluates the impacts of six urban centers. If the agency selects five urban centers as the preferred alternative, it is possible that the impacts would have been covered by the range of alternatives in the EIS.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123