Is a novated subcontract under clause 21.4 the same as a nominated subcontract ?
No, but in some respects the process is similar. However as the outgoing party to the novation agreement, the Principal will obtain a release from the specified consultant, contractor or supplier. The Principal s place under the contracts with Consultants, contractors or Suppliers is taken by the Contractor.