Is 24 months the period of performance for any training projects or fast-track training?
The period of performance for fast-track training is 24 months. The period of performance for training projects that are not fast-track training projects is 36 months. Training projects with costs that exceed the costs allowed in the fast-track training matrix and those with lower costs estimates than that allowed in the training matrix are examples of training projects that do not qualify as fast-track training requests. If we include ten project milestones, is that acceptable to TSA and FEMA? Yes. Investment Justification (IJ), Section IV C, directs applicants to provide up to ten project milestones. However, applicants should only list as many milestones as necessary and include only those major milestones that are critical to the success of the project. Where do we find the Information Bulletins (IB) discussed here? The FY2009 IBs and some FY2008 IBs that are relevant to the TSGP are available on the TSA website at: www.tsa.gov/grants under the FY2009 and FY 2008 WebPages, respecti