Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

In the cutaway, there is a 16’ x 16’ clearance for cars, then there is a multi-layered cake over the ROW. How deep is each layer and what is the purpose?

0
Posted

In the cutaway, there is a 16’ x 16’ clearance for cars, then there is a multi-layered cake over the ROW. How deep is each layer and what is the purpose?

0

There are two general areas – the beam areas and the trench areas. Working from the bottom up for each: Beam Areas: Fireproofing (1″) to protect the deck structure; Concrete Box Beams (4’ – 6″) to support the weight of the park elements; Concrete slab (8″) to provide working platform for construction, support park elements; Waterproofing/drainage mat (1/2″) to collect moisture for plants, prevent seepage into tunnel; Soil (varies, 12″ minimum) for plant growth. Trench Areas: Fireproofing (1″) to protect the deck structure; Concrete trenches (8″) to support the trees and utilities; Waterproofing/drainage mat (1/2″) to collect moisture for plants, prevent seepage into tunnel; Lightweight fill and soil (3.7’ lightweight fill, 2’ soil typical) for plant growth or soil and trees.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123