Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

If the verifier is no longer checking the design, is there a requirement to submit drawings with a building warrant application?

0
Posted

If the verifier is no longer checking the design, is there a requirement to submit drawings with a building warrant application?

0

Yes, drawings need to be submitted as they were under the previous system. This is to enable Building Control to check on construction and also acts as a record of the construction/approved warrant. It is advisable to refer to the BSD Procedural Handbook (available on the BSD website www.sbsa.gov.uk) which is essential reading for all those who wish to become registered.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123