Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

If an EA fails to conduct an informational meeting or meet the requirement of a substitute meeting, can the EA still submit the application package to the CIWMB for concurrence?

0
Posted

If an EA fails to conduct an informational meeting or meet the requirement of a substitute meeting, can the EA still submit the application package to the CIWMB for concurrence?

0

Answer 5: No; the EA is required to conduct the informational meeting or meet the substitute meeting requirements prior to submitting the application package to the CIWMB for concurrence and to include in the package a summary of comments received at the informational meeting and, where applicable, any steps taken by the EA relative to those comments. Per Section 21650(g) “No later than 60 days after the application package has been accepted as complete and correct and after conducting an informational meeting if required by Sections 21660.2 and 21660.3, the EA shall mail to the CIWMB the following: ” Title 27, Section 21660.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123