If a State DOT uses the design build concept to build a project, what is available to value engineer?
A State’s decision to use design-build as their method to design and construct a project does not remove the VE requirement. In such cases, State DOTs should perform VE studies on project information developed during the environmental and/or preliminary engineering phase. It is not practicable to perform a VE study in the design-build contract phase.