Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

If a self schedule is submitted for a unit at LSL, will the bid curve still be used to dispatch the unit in the Real Time Market or will the unit remain at LSL?

0

For Real-Time operations the QSE with Generation Resource is to submit either an Energy Offer Curve or Output Schedule and SCED will use either one to send Base Points accordingly. Self-schedule is used only for settlement in associating a Resource with a Load Zone.