Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

If a DBE has been used on the Schedule of Participation, what are the steps that must be taken in order for the prime to make changes to their contract?

0
Posted

If a DBE has been used on the Schedule of Participation, what are the steps that must be taken in order for the prime to make changes to their contract?

0

A request must be submitted in writing to the EPM, who will then submit it to the DBE Program Manager. All reasons for the change and the firm the prime plans to use in their place must be included in the request. For more detailed information, please see the DBE Program page or refer to the MDT DBE Program Guidelines.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123