I imported schedule from Microsoft Project to RiskyProject. Are any potential differences?
In most cases, if you import your project schedule from Project, the projects in both applications will be identical. However, there are specific cases that may cause slight differences: 1. RiskyProject currently does not support split tasks. However, RiskyProject will import work calculated using split tasks. RiskyProject does not have task usage or resource usage views. 2. RiskyProject calculates task duration differently than Microsoft Project in cases where resources that have different calendars are attached to the same task. However, even in these cases, start and finish times of the tasks will be identical. 3. RiskyProject does not support overtime rates. 4. RiskyProject does not import resource groups. Each resource is imported individually. 5. RiskyProject does not support the earned value method Percent work completed. Instead, it uses Percent completed. 6. RiskyProject does not support certain constraints supported by Microsoft Project, for example Finish No Early Than. The