Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

I have programmed a cooling rate of 400 degrees F per hour, which should take 4 hours to cool down to 100 degrees F. Why is the kiln taking 7 hours to cool instead of 4 hours?

0
Posted

I have programmed a cooling rate of 400 degrees F per hour, which should take 4 hours to cool down to 100 degrees F. Why is the kiln taking 7 hours to cool instead of 4 hours?

0

The controller’s cooling rate is limited by the cooling rate of the kiln’s insulation. If the kiln takes 7 hours to cool to 100 degrees, then the controller cannot speed up the cooling rate, even if you program a FULL rate. The purpose of a …

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123