Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

I cannot edit the dates of the tasks that are shown in gray in Plan View. Why is that ?

dates edit Gray Plan tasks view
0
Posted

I cannot edit the dates of the tasks that are shown in gray in Plan View. Why is that ?

0

The tasks that are shown in gray color are the Summary tasks and they are non-editable. Going by their name, they only represent the sub-task under them. The date represents the minimum of the Start dates and maximum of the Finish dates of all the tasks that come under this Summary task and hence cannot be edited.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123