How would refuse vehicles access the site?
The refuse vehicles would travel entirely via the main roads which serve the Four Ashes Industrial Estate, but would do so in accordance with a Traffic Routing Plan designed to minimise the impact of Heavy Goods Vehicle (HGV) traffic on sensitive routes. A new signalled controlled junction at A5 / Vicarage Road is to be installed by the County Council to improve local highway safety in the area and would form part of the Traffic Routing arrangements. The majority of waste deliveries would be during the normal working day Monday-Friday, but there will also be some lorry movements outside of these hours and at weekends as envisaged by the previous planning permission. A detailed breakdown and analysis of traffic movements will be provided as part of the planning application and will remain very much in line with those movements considered acceptable when permission was granted for an Energy from Waste facility at the site in 2009. Approximately 100 lorries would deliver waste to the site