How will this design address the flooding that occurs in the park? Will this project prevent flooding in Crabb Avenue and Longwood intersection?
Two projects are currently being designed to address flooding, the Longwood Storm Drain Upgrade (street flooding) and Maryvale Stormwater and Park Improvements (park flooding). The Longwood project will upgrade pipes on City property to prevent the frequent street flooding. The Maryvale project will replace an existing 42-inch pipe with dual 48-inch pipes. These existing storm drain pipes are both undersized and do not meet current design standards. These projects will help minimize flooding, but in the event of larger storms, such as the storms in late June 2006, flooding will still occur but the frequency and intensity of these events will be reduced.
Related Questions
- Can design changes be added later in development, or even well after a project is completed? What do you provide as far as post-sale services, such as website maintenance?
- How will this design address the flooding that occurs in the park? Will this project prevent flooding in Crabb Avenue and Longwood intersection?
- What is the turn-around time for our design project?