Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How will the requested demonstration be handled with respect to the energy market settlements prior to ASM Phase II?

0
Posted

How will the requested demonstration be handled with respect to the energy market settlements prior to ASM Phase II?

0

During the startup and minimum run time of the asset, the asset will be treated as a self-scheduled generator. At the end of the minimum run time, the dispatch software will be allowed to dispatch the generator economically, to either remain on line or to request the unit to shut down. Note: Any time after the demonstration period (usually 30 minutes), the generator operator may opt to do any of the following: remain on line for the remainder of the minimum run time, waive the minimum run time, or request a self-schedule for the generator to remain on line. The generator operator will have the option of requesting a self-schedule with the intention of performing a seasonal claimed capability audit. In this situation, if the ISO New England Control Room Operator has accepted the request to self-schedule, the Lead Participant is responsible for ensuring that the CCA requirements are met, including remaining self-scheduled, if necessary, for remaining on line for the amount of time requir

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123