How will the construction of Phase II impact the outlook from the low-rise floors?
There will be no exterior jump elevators attached to the building during the construction of Phase II. All construction materials will be lifted to the high-rise floors of the building using the construction crane and the construction hoists to be located in the high-rise elevator bank. The majority of the construction materials will be taken by the construction crane from a picking area on the northeast corner of the adjacent plaza.