How was the cost to purchase and renovate the building determined?
The decision to purchase and improve the property at 520 South First Street followed a comprehensive planning process and project assessment involving the Museums board of trustees, key community leaders and staff. Careful cost estimating, including contingencies for inflation has led to the overall project budget of $7.64 million. Remaining project elements yet to be funded are fixed costs and not subject to unforeseen increases.