How quickly can the Environmental review process be completed before starting the Cultural review process?
Within 5 working days of receipt of the information from the Project Engineer, the Environmental Section will meet with the US Fish and Wildlife Service to obtain clearance. If further review is required, the Environmental Section will coordinate with the local US Fish and Wildlife Service Wetland Management District office to review the location(s) in the field. The purpose of this is to identify avoidance areas and areas that can be used. This additional review in the field may take up to an additional 10 working days to schedule.