Time to completion of any building depends on the complexity and size of the building. Once the working drawings are complete and the timbers have arrived, a 2500 sq ft timber frame would take between four and six weeks of shop time to fabricate. Approximately one week to assemble and erect the timber frame and two weeks to install the roof and wall enclosures. From start of fabrication to enclosure finish, a project of this size would take approximately 6 to 8 weeks.