How much asbestos must be present before the Asbestos NESHAP notification applies to renovation projects?
A Notice of Asbestos Renovation or Demolition is required for facilities with at least 80 linear meters (260 linear feet) of regulated asbestos-containing materials (RACM) on pipes, or 15 square meters (160 square feet) of RACM on other facility components, or at least one cubic meter (35 cubic feet) of facility components where the amount of RACM previously removed from pipes and other facility components could not be measured before stripping. These amounts are known as the “threshold” amounts.