Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How many times was the Balkans Support Contract extended?

0
Posted

How many times was the Balkans Support Contract extended?

0

Three times. The first extension, May 28, 2004, through November 23, 2004, occurred under a standard Federal Acquisition Regulation clause included in the Balkans Support Contract, Option to Extend Services. This clause allowed for the period of performance to be extended for no more than six months. This extension is not considered a sole source extension since the clause was included in the original competitively-awarded contract. The second extension was for the period November 24, 2004, through April 30, 2005. The third extension was for the period May 1, 2005, through April 30, 2006, with two option periods (May 1, 2006, through October 31, 2006; and November 1, 2006, through January 31, 2007). The second and third extensions were processed fully in accordance with federal statutes, the Federal Acquisition Regulation, and implementing regulations to the FAR. They were processed through the Headquarters of the Army Corps of Engineers and approved at the Department of Army level (by

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123