Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How many return truck journeys will be required to build the foundations, and the towers and other equipment? Will there be an on-site mixing plant?

0
Posted

How many return truck journeys will be required to build the foundations, and the towers and other equipment? Will there be an on-site mixing plant?

0

Each of the four bases would use 350 m3 of concrete (say 800 tonnes each) and typical ready-mixed concrete truck capacity is 6m3 or 8m3, so there would be about 200 return truck movements, over a period of four days. There would not be an on-site mixing plant.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123